AD-09 · Architecture Governance / Platform Architecture

Resolve hard-to-reverse decisions before execution

IMPLEMENTED · the instrument’s decision cycle, not the state of the programmeSUPPORTED
The decision
Let the reversible work carry on, and set a stop line before executing the decisions whose cost of correction would rise materially once the infrastructure existed.
Why it mattered
The platform proposal could move on to detailed design, but a few decisions would be frozen in practice the moment the infrastructure was created. Finding the mistake afterwards would mean rebuilding, or accepting a relevant risk late.
The options
Approve without conditions; reject the proposal outright; or allow it to proceed with conditions and gates differentiated by the moment each decision had to be closed.
The trade-off
The model demands more discipline in follow-up and evidence, but it avoids both building first and correcting late, and stopping work that is still reversible.
What changed
The irreversible decisions were separated from the activities that could carry on without committing them.
The outcome
The assessment let design and preparation carry on, but stopped cluster creation until three Day-1 decisions were closed.

Reusable principle

The harder a decision is to reverse, the earlier it must be reviewed and the more evidence should be required to approve it.

Related case study

Architecture Governance Before Provisioning

Summary of a documented architecture decision. Method, mechanism and supporting evidence are not published.